Share This

Showing posts with label slopes. Show all posts
Showing posts with label slopes. Show all posts

Saturday, 31 August 2019

Design engineers at fault in landslide tragedy, act against negligent engineers

Design engineers at fault in landslide tragedy | The Star Online
https://rightways.files.wordpress.com/2017/10/8723e-penang2blandslide_tanjung2bbungah1.jpg

GEORGE TOWN: The State Commission of Inquiry (SCI) tasked with investigating the Tanjung Bungah landslide in October 2017 has found the design engineer of the slope primarily responsible for the incident that claimed 11 lives.

The SCI, in its 116-page report made public, has recommended that the engineer be investigated by the police under Section 304A of the Penal Code for gross negligence.

Besides the engineer, the commission found another design engineer responsible for being “contributorily negligent” for allowing excavation to be carried out without design, engineering calculations and supervision.

Chief Minister Chow Kon Yeow said the commission found that the slope failure was a man-made tragedy and entirely preventable if those in charge had taken necessary and proper steps to ensure the stability of the slope and the safety of the workers.

“The landslide did not develop overnight, it was a disaster waiting to happen over a period of time.

“There were ample warnings which were sadly unheeded or inadequately heeded,” Chow said of the report at a press conference at his office in Komtar here yesterday.

Chow said the report, dated July 22 this year, was a result of public hearings conducted over 26 days with testimonies from 28 witnesses.

“The commission also considered voluminous documents, reports, photographs and drawings, as well as the opinions of six expert witnesses.

“The report provides further analysis of the background facts, excerpts of testimonies recorded during the hearings and findings on liability against several parties,” he said.

The commission also found the Occupational Safety and Health Department negligent for failing to take adequate steps to ascertain the extent of the danger posed by the unsafe slope, by not promptly issuing a prohibition notice after its visit to the site on Aug 18, 2017, which was two months before the fatal incident.

Chow said copies of the report would be sent to the police, Attorney General’s Chambers, Board of Engineers Malaysia and other authorities involved.

“The report also contains nine recommendations that the commission hopes will serve as guidelines and prevent such incidents from recurring,” he added.

On Oct 21, 2017, a temporary slope in the construction site of a high-rise apartment block in Tanjung Bungah collapsed while workers were trying to stabilise it. Tonnes of earth crumbled, killing 11 workers.

The full SCI report can be bought at Level Three, Komtar, for RM50 per copy between Sept 3 and 30. For more details, call 04-650 5480.- Source link

Chow: Agencies have to act against negligent engineers

Penang chief minister Chow Kon Yeow

 GEORGE TOWN: It is up to the relevant agencies to take action against the consultant engineers who were found negligent, resulting in the Tanjung Bungah landslide tragedy, says Chief Minister Chow Kon Yeow.

“It is up to the agencies and the police to take action as recommended by the State Commission of Inquiry (SCI).

“I have also directed the Town and Country Planning Department, Penang Island City Council, Seberang Prai Municipal Council and other related agencies to come up with recommendations to improve hill development.

“It was discussed at the State Planning Committee meeting and I have directed state housing, town and country planning and local government committee chairman Jagdeep Singh Deo to head the committee and come up with the recommendations within a month, ” said Chow at Komtar here yesterday.

It was reported that the SCI tasked with investigating the Tanjung Bungah landslide in October 2017 had found the design engineer of the slope primarily responsible for the incident that claimed 11 lives.

The SCI, in its 116-page report made public, had recommended that the engineer be investigated by the police under Section 304A of the Penal Code for gross negligence.

Besides the engineer, the commission found another design engineer responsible for being “contributorily negligent” for allowing excavation to be carried out without design, engineering calculations and supervision.

Penang Island City Council engineering director A. Rajendran, who was also present at the press conference, said the stop-work order on the project was lifted after the developer completed mitigation works.“However, different engineers have been overseeing the project since work resumed some time ago, ” said Rajendran.

On Oct 21,2017, a temporary slope at the construction site of a high-rise apartment block in Tanjung Bungah collapsed while workers were trying to stabilise it.

Tonnes of earth crumbled, killing 11 workers. - Source link

Read  more:




Related posts:

Penang landslide tragedy, plea went unheeded, no one listened !

 

Don’t allow another landslide tragedy to happen !


Penang landslide, whose faults?

 

Huge landslide in Tg Bungah hill


 

Landslide tragedy caused by slope instability, was a Construction mishap, not landslide!

 

Landslide nation, Malaysia ranks highly for landslides


 Penang landslide tragedy, why it happened?


 

 Penang Landslide occured days after remedial works started 

 

Penang floods and landslides, looking beyound natural causes!


Cracked drain causes road cave-in, house nearby on brink of callapse

 

Penang govt rapped over hill slope development

 

Invalid drainage and construction damaged nearby houses since 2014 must complete its mitigation quickly!

 

Penang floods, support pours in for dialogue

 

Penang Paya Terubong Residents living under shadow of fear!


Call to reassess Penang hillside projects, councillor addresses full council meeting of MBPP


 

Hills, landslides, floods and damaged houses: What to do?

 

Penang landslides & flooding are natural disasters man-made?

Has Penang Island’s growth & development become a hazard to life?

 

Wednesday, 1 November 2017

Penang floods and landslides, looking beyound natural causes!

Seeking solutions: Penang Forum member and soil expert Dr Kam Suan Pheng giving her views during the dialogue session themed ‘Penang Floods: A Call for Action’ held at Teow Chew Association in Chulia Street, George Town.
 (Top pic, front from right) Pulau Betong assemblyman Datuk Dr Muhammad Farid Saad, state Opposition Leader Datuk Jahara Hamid and Penanti assemblyman Dr Norlela Ariffin among the participants.
From left) Sim, Cheah, Dr Norlela, Jahara, Shah Headan, Lee and Yap occupying the front row at the dialogue on floods organised by Penang Forum.


Expert: Debris clogging waterways among reasons for flash floods

Some 200 people comprising mostly politicians, experts and residents gather in a dialogue session to discuss the long-standing problem plaguing Penang. Many voice their concerns that over-development in the state could be the cause of the headache.

HEAVY rainfall and high tides are natural causes of floods which cannot be avoided.

However, soil expert and scientist Dr Kam Suan Pheng said there were also other reasons that caused the constant flash floods in Penang.

She said limited capacity to channel off discharge and surface flow which led to water accumulation downstream were some of the causes that resulted in flash floods.

“These issues have been addressed in flood mitigation.

“However, we also have to tackle the causes of increasing impermeable surface areas and debris clogging up waterways, which are also the root causes of flooding problems,” said Dr Kam in her talk on ‘Understanding the Causes of Floods and Seeking Solutions’ yesterday.

Dr Kam, who is also a Penang Forum member, said having proper planning on land usage and development controls, creating more urban spaces and parks besides river bank protection were also vital in flood prevention.

“Stringent monitoring on development projects and protection of hill land and hillslopes are important.

“To do so, policy and legal instruments have to be deployed, while environmentally sensitive and ecologically friendly structural and non-structural solutions should be adopted,” she said.

Dr Kam was one of the speakers at a dialogue session themed ‘Penang Floods: A Call for Action’ held at the Teow Chew Association in Chulia Street.

<< Stringent protection of hill land and hillslopes are vital, says Dr Kam.

Joint Resident Associations of Bandar Baru Ayer Itam chairman K. Suthakar said that for the past two to three years, residents living in Bandar Baru Ayer Itam have been suffering from flash floods.

He said there were some 20 housing schemes in the township comprising 10,000 housing units with a population of 16,000.

“The residents had to face the brunt of it when the whole city was underwater on Sept 15.

“I visited the retention ponds in Lebuh Rambai and Desa Permata Bandar Baru Ayer Itam on Saturday to check whether the ponds have been deepened.

“Sadly, nothing has been done,” he said.

He asked some of the state assemblymen, who were present at the dialogue session, to raise the issue when the state assembly convenes on Thursday.

When hills are at their natural state, they will not collapse, says Aziz Noor. When hills are at their natural state, they will not collapse, says Aziz Noor. >>

Environmental, health and safety consultant Aziz Noor, in his talk on ‘Implications of Hillside Development’, said landslides commonly happened on hillsides or slopes that were cleared.

“When the hills are at their natural state, they will not collapse.

“But when the natural state is violated with the slopes being cut, then landslides are bound to happen.

“Whenever there is a downpour on the cut hill slopes, there would be mudslides contributing to muddy flash floods as well,” he said.

Filepic of recent flooding in Taman Thean Tek, Ayer Itam, Penang.

The dialogue session saw a packed hall of almost 200 people, comprising mostly residents and representatives of residents associations who were affected by the recent flash floods.


Several state assemblymen and politicians from both sides of the divide also turned up at the event organised by Penang Forum and Residents Association of Penang.

Among those present were Penang Barisan Nasional chairman Teng Chang Yeow, state Opposition Leader Datuk Jahara Hamid, Pulau Betong assemblyman Datuk Dr Muhammad Farid Saad, Teluk Bahang assemblyman Datuk Shah Headan Ayoob Hussain Shah, Kebun Bunga assemblyman Cheah Kah Peng, Penanti assemblyman Dr Norlela Ariffin, Machang Bubuk assemblyman Lee Khai Loon, Pulau Tikus assemblyman Yap Soo Huey and Bayan Baru MP Sim Tze Tzin.

Sources: The Star by Logeiswary Thevadas

Engineer: Look out for ‘ticking time bombs’ from hill slopes


GEORGE TOWN: A geotechnical engineer has warned the authorities that steeply-cut hill slopes are “ticking time bombs” that need constant monitoring and maintenance.

Zeezy Global geotechnical and environmental consultant Aziz Noor said in view of the Tanjung Bungah landslide on Oct 21 that took the lives of 11 workers, all authorities, not only in Penang but throughout Malaysia, should keep an eye on all steep slopes as disaster might strike at any time.

He said although a hill slope might appear fine from the outside, it could be on the brink of collapse due to water pressure and vibrations from the surrounding environment.

“Most of these slopes are clay mixed with sand. Clay has an affinity ( to stick together). At particle level, they can hold up.

“When water comes down steep slopes they break the affinity of these particles. And yet they still hold up but it just speeds up the time of the collapse.

“That is why they do not fall right away. They are a time bomb, a disaster waiting to happen,” he said at a talk hosted by Penang Forum today.

Aziz, an American-trained environmental and geotechnical expert, was manager of an independent consultant engineering firm investigating the aftermath of the Highland Towers collapse in Ulu Kelang, Selangor, in 1993, in which 48 people were killed.

He said hills cut beyond their “natural angle” were the ones to watch out for.

“A hill slope that is cut beyond its natural stable angle is not a stable slope. Such slopes are at high risk of failure and can end up in landslides.

“When you have bare slopes like that, the portion of runoff is large; the steeper the slope, the faster the ‘teh tarik’ (mud slide) comes down.

“Basically, when the water runs off faster, the more erosion it causes, and the faster it will go down to lower-lying areas and cause flash floods with silt,” he said.

Aziz said to prevent such disasters from happening, engineers ought to cut hills at a more natural angle and ensure drain holes are built into them.

He said drain holes would release the “water stress” that might be building up beneath the slopes.

Aziz stressed that these measures were not one-off solutions and required constant monitoring from all parties.

“Ordinary folk might think, okay, looks like a nice concrete wall. But you do not know what is going on underneath, and hence, you need to maintain the hillslopes from time to time.

“That is why you see the slopes on our PLUS highway are constantly being maintained. It is something you do not mess around with,” he said.

Aziz said many construction sites cut corners by placing plastic sheets on cut hillslopes, which would not help much in preventing landslides.

“This is akin to putting a band-aid on a very sick person,” he said.

On the Tanjung Bungah landslide, Aziz said the state authorities must beef up their monitoring teams and place them on full patrol at all sites in the state.

“We need all the ‘jabatan’ (departments) to wake up and not sleep behind the wheel. Present-day laws are adequate to enforce and punish those who flout the law.”

Sources: Free Malaysia Today

Penangites upset with DAP reps for skipping dialogue


Front row, from right) Penang Barisan Nasional chairman Teng Chang Yeow, Pulau Betong representative Muhammad Farid Saad and state opposition leader Jahara Hamid at the Penang Forum dialogue on flood woes and hill site developments. – The Malaysian Insight pic, October 29, 2017.

RESIDENTS associations in Penang today were upset that most of their elected representatives skipped a dialogue on flood woes and hill site developments, as local civil society groups continue to push for a moratorium on hill projects.

Penang Forum, a coalition of local civil society groups, had invited the state’s elected reps, but fewer than 10 turned up at the dialogue that drew about 200 people to the Teochew Association in George Town.

The assemblymen seen among the crowd were state opposition leader Jahara Hamid (Teluk Air Tawar), Muhammad Farid Saad (Pulau Betong) and Shah Headan Ayoob Hussain Shah (Teluk Bahang) from Barisan Nasional (BN); and Cheah Kah Peng (Kebun Bunga), Dr Norlela Ariffin (Penanti) and Lee Khai Loon (Machang Bubok) from PKR.

Pulau Tikus rep Yap Soo Huey was the sole DAP assemblyman present while the only MP at the dialogue was PKR’s Sim Tze Tzin of Bayan Baru. The only other DAP member present was Penang Island City councillor Syerleena Abdul Razak.

Also present were Penang BN chairman Teng Chang Yeow, several Gerakan leaders, and Penang Front Party’s Patrick Ooi, who has been critical of the Penang government in the past.

Jahara said the BN reps in the Penang legislative assembly would table a motion to call for all hill land and slope projects to be halted.

“We are not here to point fingers, but fingers have to be pointed at the authorities,” she said.

Norlela, one of the most vocal PKR reps on local developmental issues, said she hoped Pakatan Harapan and BN could set aside their differences to solve flood woes and developmental issues in the state.

Norlela was one of five PKR government backbenchers who abstained from voting to reject a BN motion on land reclamation during the state legislative assembly in November 2015.

DAP holds the most seats in the Penang legislative assembly with 19 out of 40. PKR has 10 while PAS has one seat. BN’s Umno holds the remaining 10.

In a press conference last week after a landslide in Tanjung Bungah killed 11 construction workers, some residents association reps warned the state government that it could lose votes if it continued to allow hill site developments and ignored the people’s objections.

At the dialogue today, the joint residents association rep for Bandar Baru Ayer Itam, K. Suthakar, took a dig at the elected officials when speaking about flood woes in his area. He said Lebuhraya Thean Teik had “turned into a river” when a bad flood hit last month, causing residents to miss work and school.

“Why do they become elected reps? Because they want to serve the people, to solve their problems. But after the election, you don’t see them for three or four years. People are crying for help but you have no time to come,” he said.

Tanjung Bungah Residents Association chairman Meenakshi Raman also said she had expected more than 10 elected reps to attend the dialogue.

“We are disappointed that not many could attend. We had hoped to see more DAP reps,” she said.

It was learned that DAP had an internal party programme at the same time this morning on mainland Penang in preparation for the party’s special congress on Nov 12 to re-elect its central leadership committee.

Meenakshi said the residents association and other civil groups, which recently criticised the state government over hill site developments and flash flood incidents in Penang, were still willing to engage the powers that be in dialogue.

This was despite the association not getting replies to letters it recently sent out to all Penang assemblymen and MPs on its demands to solve flash flood problems.

“We are ordinary people. We have nothing against them, but some (leaders) have accused us of being arrogant. Elected reps must be accountable. There is nothing wrong with the people asking the state government and their YBs (assemblymen) what they are doing,” she told The Malaysian Insight after the dialogue.

Climate change

Meanwhile, Dr Kam Suan Pheng, an expert in geographical information systems, told the dialogue session that floods in Penang were caused by both weather conditions and human activities, adding that the situation would worsen with climate change.

“Since 2003, the emerging trend for rainfall is increasing. Flash floods will be more frequent, happening at lower rainfall thresholds.

“With climate change, we can expect heavier and more intense rainfall,” she said, adding that Penang’s urban drainage was not well planned enough to prevent floods.

Kam said the authorities must tackle the root causes with proper land use planning and development control, stringent protection of hills and river banks, strict monitoring of development projects, and by increasing the number of urban parks.

She said the authorities must also look beyond the environmental, drainage, transportation and social impacts of individual projects, use existing laws and policies and adopt eco-friendly solutions.

Aziz Noor – a consultant with more than 30 years’ experience in areas of environment, health and safety in Malaysia and overseas – said Penang should take the recent Lembah Permai landslide as a wake-up call.

“Legislative controls are more than adequate but compliance is sporadic. Enforcement has been weak,” said Aziz, who is managing director of Penang-based consulting firm Zeezy Global.

Another speaker at the dialogue, lawyer Agatha Foo, said legally, the state should stop development on ecologically-sensitive land over 76m above sea level and on slopes over 25 degrees gradient using existing laws and guidelines.

She also said the authorities could impose strict enforcement, and seek a jail sentence for company directors whose firms violate the law as a more effective deterrent than fines. – October 29, 2017.

Looi Sue-ChernSource: The Malaysian Insight by


Related Link:

Sole DAP rep heckled at Penang woes talks


https://youtu.be/YQM8N0GTuYM

The day the earth moved - Analysis

Penang's 'balding' Bukit Relau under the spotlight

Group: Stop approving hill slope projects - Metro News

Forum gets tepid response from reps - Nation

Project's final approval came from Penang authorities - Nation

Penang DAP: We respect Teh's decision to quit party - Nation 

Tanjung Bungah rep wants to quit DAP - Nation

Related posts:

2 structures collapse due to incompetent engineers and irresponsible officer of MPPP

(From left) Dr Kam will deliver a talk on ‘Understanding the Causes of Floods and Seeking Solutions. State assemblymen expressing inter...
Some representatives of the 24 residents associations and management corporations showing messages urging the state to resolve the flood...
Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'...
https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto's blog showing an active s..

Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ..

https://youtu.be/4qaOB1n5tgA GEORGE TOWN: The Penang Island City Council has lodged a police report against the consultant of the aff...

Put on hold: A view of the site for the development of four apartment buildings in Paya Terubong, Air Itam. GEORGE TOWN: Since the ...

Humans Are Destroying the Environment   PETALING JAYA: They are supposed to be guardians of the environment, and yet “certain enforcem...
PETALING JAYA: Some RM40mil from the Skills Development Fund Corp is believed to have been siphoned off by those tasked with utilising i.,

Tuesday, 5 September 2017

Invalid drainage and construction damaged nearby houses since 2014 must complete its mitigation quickly!

Underground Pipe Culverts from IJM Trehaus site on the left and nearby pond on the right

Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project. 
Approximate Coordinates : 5°20'38.47"N,100°16'52.82"E
Reported  in August 2016. Photos taken in November 2016 and 2014 by Penang Forum
PHW Report 




https://hillclearinginpenang.ushahidi.io/views/map

Sources: Penang Hills Watch (PHW) | Penang Forum

Hill clearing activity by IJM Trehaus Project


Clearing and construction for a condo and semi-detached housing project, Trehaus, reported in http://anilnetto.com/ 26 Aug 2016. Photo taken in 2014 ...

IJM sign-boards
Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.

Underground Pipe Culverts from IJM Trehaus site on the left and nearby pond on the right

  Two invalid pipe culverts formed sinkholes at BJ Cove houses

Originally, there were two natural rivers/streams from the IJM Trehaus site and a nearby pond. No proper drainage system was implemented when housing development started, only two invalid hidden underground pipe culverts were built to channel the waters from the Bukit Jambul hill to Relau district.

The invalid underground pipe culvert from the IJM Trehaus project directly converged at BJ Cove houses from another invalid underground  pipe culvert from a nearby pond were burst, caused soil erosion, house slabs collapsed, multiple wall cracks, PBA water pipe burst, floods, sinkholes (by two pipe culverts converged in red) and damaged  to  BJ Cove houses due to blockages of waters whenever rains and because of lack of drainage system there.  The sinkhole which later converted into a manhole by IJM,  is a clear sign of soil erosion under the ground.

It is a common sense that waters from the natural rivers or streams are naturally running, seeped  through underground even the surface is covered by land-filled soil or with man made culverts.

Therefore, damages to houses were caused by severe soil erosion due to water movement under the road and buildings. 

The following shows the invalid underground pipe culvert from the IJM Trehaus site behind BJ Cove houses at Lintang Bukit Jambul 1:


IJM Underground Pipe Culvert to BJ Cove houses 2018
Waters rising from the IJM Pipe Culvert behind BJ Cove houses 2018
Waters are flowing back from another pipe culvert at IJM site to BJ Cove houses 2018

IJM Underground Pipe Culvert at bottom to BJ Cove houses 2018

IJM modifying/constructing their underground pipe Culvert in 2014 to BJ Cove Houses
IJM modifying/constructing their underground pipe Culvert in 2014 to BJ Cove Houses

IJM Underground Pipe Culvert to BJ Cove Houses 

IJM Drains
IJM Drain Waters go  to the underground Culvert
IJM Underground Pipe Culvert next to BJ Cove Houses



The above and below show the bottoms of  IJM underground pipe culvert 







Waters gushing down from IJM Trehaus site to BJ Cove houses:

Waters flow from IJM Trehaus to BJ Cove houses
 

Waters gushing down from IJM Trehaus site to BJ Cove houses




Waters from IJM site stucked at behind BJ Cove houses

The nearby pond besides IJM Trehaus site:

IJM Hill cutting and hill Clearing 2014

Serious Drainage Issues


The Department of Irrigation and Drainage (DID or JPS) has just started in September 2017 constructing the drain from the pond to divert waters:

A drain under construction by JPS to divert waters from the nearby pond
Drain waters flow plan under construction by JPS to divert waters from the nearby pond

 Letter from Penang Dept of Irrigation and Drainage (DID or JPS) in 2015 blamed IJM  failure to comply with sedement control plan (ESCP) when its Trehaus started in 2014.



Clearly, the underground pipe culverts leaked and waters seeped through the ground and multiple cracks,  as it did not happen immediately but over a period of time!




Developers dishonored directives/letters issued by Penang City Council (MBPP - Majlis Perbandaran Pulau Pinang) in 2015 to rectify the damaged house






Developers have not completed their committments to rectify the damages despite  acknowledged their liability as per letters from Worldwide Venture Sdn Bhd, an subsidiary of IJM Land since 2014!


 
 


Despite the underground pipe culverts declared invalid by JPS and the Penang City Council's (Majlis Perbandaran Pulau Pinang, i.e. MBPP) issued stop work orders directing the developers, Worldwide Venture Sdn Bhd, a subsidiary of IJM Land to rectify the damages within 1 and 2 weeks time since 2015 (as per the above attached letters), the multiple wall cracks, slabs collapsed, PBA water pipes burst, leakage charges, damaging ceiling, electrical DB board, and tiles fallen, broken/popped up,  are still pending settlement and remedial works to be carried out by parties responsible for the damages since 2014 !!



IJM Land only started in December 2017 constructing new drainage to divert waters from Trehaus Site to the pond and underground pipe culverts:


Pictures show IJM only started in December 2017 constructing drainage system to divert waters to the nearby pond and underground pipe culverts


Waters are flowing back to the pond during heavy rain 2018
Waters from IJM site overflown to the pond 2018
For waters to flow out smoothly, the pond must level up with more soils, 2018


Waters in the pond gone up during heavy rain 2018 - must build a wall  to prevent waters from seeping thru houses.
Waters cannot move out smoothly due to obstructions which are being removed by a man  2018
 

It is important that the pond should be made a dried pond instead of existing wet pond on the following reasons:

i) The area was originally a natural river/stream where waters will still be naturally running, seeped through underground even when the underground culverts are to be closed/abandoned later.

 

ii) More waters were being diverted from the IJM site to their underground pipe  culvert and to BJ Cove houses.

 

iii) Now, drain waters from IJM site are being channeled back to IJM pipe culvert to BJ Cove houses at Lintang Bukit Jambul 1 where a manhole next to house no. 20 constructed by IJM is not closed despite it has been declared invalid and illegal by JPS!  This poses concerns to residents at BJ  Cove houses.

c
IJM Drain water Pipe Culvert Site to BJ Cove houses
IJM Drain water Pipe Culvert Site to BJ Cove houses
Waters stuck behind BJ Cove houses at IJM site 2018

IJM Drain  waters  gushing  down to pipe culvert

Sinkhole at house 20 is covered up by IJM's underground pipe culvert from  IJM Trehaus

 

The damaged houses are still pending, not being completely rectified to date !

Damages appeared after IJM began construction works in 2014, like hill clearing, rock-blasting, piling and digging culvert at Trehaus site.  As a result, sinkholes appeared, floods, waters seepage through multiple cracks on the ground, walls, tiles fallen from roofs and popped up from the ground due to vibration from rock-blasting and piling works.

 
Sinkhole converted to manholes (2 in cycles) at BJ Cove houses are visible from the top of IJM Trehasu site

Pictures showing floods, sinkholes at Lintang Bukit Jambul 1, 11900 Penang,  damaged to BJ Cove houses, cracks, waters leakages seeped through the cracks, slabs collapsed, ceilings & tiles broken & fallen, electrical DB board explosion, etc caused by severe soil erosion due to water movement under the road and buildings. The underground pipe leaked and waters seeped through the cracks!


A big Sinkhole near BJ Cove house no. 20

IJM converted the sinkhole into a manhole waters from their underground pipe culvert at Trehaus
These are IJM Manhole converted from Sinkhole:

Sinkhole at house 20 is covered up by IJM's underground pipe culvert from  IJM Trehaus


IJM converting the Sinkhole into Manhole next to  BJ Cove no. 20
Outside house drain and fence damaged by IJM during mitigation of Sinkhole
A big Sinkhole occurred due to invalid underground pipes culverts choked near house no. 20
Waters at the underground pipe culverts flown out from the house No. 20 to outside drain
 
Slabs collapsed due to cracks without compacted hardcore

Roof top Ceiling Board fallen due to strong vibration caused by IJM rock-blasting works 2014

Electric DB Board explored due to burst pipe waters seeped thru the wiring.



Waters leaked from the burst pipes entered into Bedrooms

 Multiple Cracks in Bedrooms 













Plumbers repaired the broken water pipes
















 

Truth Be Told:


The truths be told,  as echoed, reinforced and justified by recent events in  Penang floods on 15th Sept 2017,  Landslides in Tanjung Bungah on 21 October 2017, the storm on Nov 4 & 5 2017, floods again on Jan 5, 2018, and the Huge 'bleeding' landslide in Tg Bungah hill  on May/June 2018  in related posts,

.... see more on links to following reports:

https://youtu.be/ooyXvqmxbvw GEORGE TOWN: Some 20 houses located on a slope in Hong Seng Estate in Mount Erskine were flooded due

Hills, landslides, floods and damaged houses ...

Penang landslides & flooding are natural disasters man-made...  

Penang floods and landslides, looking beyound natural causes!

Penang landslide, whose faults?

Penang Paya Terubong Residents living under shadow of fear!

Penang landslide tragedy, why it happened?  

PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development  

 

We demand immediate enforcement & Actions to complete the remedial works:

 

1. The parties responsible must quickly without further delays, without condition to settle the claims and start the remedial works to the damaged houses, as both JPS has declared underground pipe culverts invalid and  MBPP has  issued stop work orders directed the developers, Worldwide Venture Sdn Bhd, a subsidiary of IJM Land to rectify the damages within 1 and 2 weeks time since 2015!


2. Enforce IJM's & MBPP' Letters/Stop-work Orders (attached in above), and divert waters from the two invalid underground pipe culverts deemed illegal at the IJM Trehaus site and nearby ponds which must be closed and grouted as a long term solution to the problems. 

 

3. Enforce a fresh cease and desist to Stop Work of IJM Trehaus construction project until the structural damages to house at 20 Lintang Bukit Jambul 1, BJ Cove have been resolved and settled the claim for damages and distress caused by the fear and danger of living in the house, without further delays and their suffering more than four years since 2014.  Repairs and remedial works must start promptly as more damages and suffering will fellow!

 

4. Beef up the enforcement and accountability not just in government agencies but also in professional bodies, like the Board Of Engineers Malaysia (BEM),  the Institute of Engineers Malaysia (IEM), etc to uphold the professional ethics, integrity and standards, to ensure public safety of the buildings and people life.

 

5. The pond must be made a Dried pond for waters to flow out smoothly, because there was originally two natural rivers/streams in the area where waters will still be running/seeping through naturally under the ground. 

 

 6.  Now, drain waters from IJM site are being channeled back their underground pipe culvert flowing to BJ Cove houses at Lintang Bukit Jambul 1 where a manhole next to house no. 20 constructed by IJM  is not closed despite it has been declared invalid and illegal by JPS!  This is a great concern to residents at BJ  Cove houses. We want JPS and MPPP to close & grout the manhole promptly.

 

7. Damaged house owners firmly reserve all their rights to take all necessary legal steps against those responsible exclusion their liabilities.


Findings from Penang Forum 

Dr Kam, a scientist, focused on expansion of impermeable surface area (caused by ill­ planned development and replacing natural ground cover such as hills, fields and trees that act as a water ­absorbing sponge) and soil erosion and landslides (caused by cutting and development in hill areas) as two factors that need special attention.

She quoted Datuk Kam U Tee, the Penang Water Authority general manager (1973~­90), as having correctly explained the Penang floods of October 2008, as follows: the floods were caused by conversion of the Paya Terubong and Bayan Baru valleys into “concrete aprons that do not retain water. The water immediately flows into streams causing flash floods even with moderate rainfall. Because of hill­cutting activities, the flowing water causes erosion of the slopes which carries mud and silt into the river beds”. ( The Star, Oct 24, 2008).


See more  ....
 




Credits - Slides presented by Environmental, health and safety consultant Aziz Noor, and scientist Dr Kam Suan Pheng at the Penang Forum event on Oct 29, 2017

See more ....



Practise true CAT for Sustainable Development

  • Penang government must provide a COMPETENT flood mitigation plan for the state starting with a comprehensive Drainage Master Plan Study and not slogan.

  • The Penang government has to be ACCOUNTABLE to the people and not private developers. In other words, ‘Politicians should be ‘wakil rakyat’ and not ‘wakil pemaju’. If certain waterways and catchment areas have to be gazetted as permanent drainage and storage areas, then so be it. 

  • The safety and well-being of the Rakyat has to come first.  In the interest of  TRANSPARENCY, Penang has to launch an inquiry into how the local council approved property developments on slopes without adequate slope protection.

 See more ...

1. Wanted: Leaders who listen !
2. Sustainable Development in Penang
3. Call to reassess Penang hillside projects, councillor addresses full council meeting of MBPP
4. Penang landslide, whose faults?



Related:   


Include Penang Forum in panel probing Bukit Kukus landslide tragedy

   

 

  At Penang landslide memorial, group questions silence of PH MPs

Consultant, contractor of Bukit Kukus paired road project slapped with ...


Risky building on hillslopes - Nation

 

Come together to save our state 

 

In Malaysia, an island drowns in its own development


Watch "Slope Stability" on YouTube


https://youtu.be/2wT2he6Numk

Penang MP rapped for asking for allocation while rejecting Budget ...

KUALA LUMPUR: A Penang Opposition lawmaker was rapped for voting ... Budget 2018 yet seeking an allocation for flood mitigation projects.

RM150mil for flood mitigation projects - The Star Online


A tempest flays the north

GEORGE TOWN: When the storm hit, everyone in the north prayed it would soon blow over.Penang flood: Precautionary power cuts in place as waters rise

Penang paralysed by floods - Nation



Irked residents to hold meeting with state representatives on Penang ...



https://youtu.be/n2vO-nsZxkY

'Bleeding' landslide worries residents - Nation

Damaged houses to be repaired - Metro News

Rep: Redevelop village to solve recurring erosion - Metro News

Residents prefer affected houses to be torn down manually

Bruised in sinkhole fall at home - Nation

Penang CM must stop blaming past govt for problems

Cracks in homes force seven Penang families to flee - Nation

Here's the proof — federal govt gave only RM443mil for flood mitigation

Former councillors claim Penang government abuse caused floods

PAS claims graft caused floods in Penang | Malaysia

Penang pays high price in storm havoc - Nation

Up to the chest in water, up to the neck with the excuses - Nation

Dept: Typhoon Doksuri caused erratic weather across Penang ...

Rapid development in Penang root cause of massive flash floods ...

Admit failure in solving floods and stop giving excuses, Penang govt told

Deluge brings chaos to northern states - Metro New

Penang floods: Body of missing woman found in Bukit Jambul river

Updated) Penang flash floods claim a life, second death due to floods ...

https://www.nst.com.my/.../updated-penang-flash-floods-claim-life-second-death-due-...
Sep 16, 2017 - ... Noor Afidah Yahunas, 30, who fell from her motorcycle into a culvert in ... by rescuers in a river near Bukit Jambul about 7.45am today, nearly 24 ... to lose balance and fall off, before she was swept away by strong currents.

Boast to end floods rings hollow - Nation

Anti-flood plan in pipeline - Metro News 

Chant: Set up unit to monitor hill projects - Nation

CAP: Halt projects in flood-prone areas until wet spell ends - Nation ...

Penang mayor Maimunah quits job to accept UN post

Hiking trail in awful condition - Metro News

Clogged drains main cause of floods - Metro News

 

  Narrow drains contribute to flooding

 The narrow drainage system which Chua claims results in flooding in the area.


 


Related posts:


Cracked drain causes road cave-in, house nearby on brink of callapse

https://youtu.be/9yXuW1pdrt4

MBPP, contractor, engineers and DOSH named as responsible in fatal Penang landslide

Kudos to Deputy Chief Minister I Datuk Ahmad Zakiyuddin for holding the four parties accountable for the Bukit Kukus landslide tragedy. The inquiry still begs a lot of questions, e.g. why was the contract given to Yuta Maju from Terengganu? Could the accident have been prevented if a proper EIA was done? It is not just a "bureaucratic hurdle" but supposed to identify risks and advise mitigation. If the authorities wish to go on with the project, it is not too late to commissi...
See more


 “This is no simple incident as nine deaths resulted from it. Very stern action must be taken against the MBPP, and that includes strong disciplinary action against the mayor and officers responsible.

“Otherwise, it will be business-as-usual in the MBPP as the officers will be allowed to go scot-free with impunity.



Come together to save our state - Letters | The Star Online

 



 

Landslide nation, Malaysia ranks highly for landslides

 


A drone picture of the collapsed beams along Jalan Tun Sardon leading to Balik Pulau on the left while Jalan Paya Terubong on the ri...
Consultant gets show-cause letter for ‘overlooking hilltop stream’ GEORGE TOWN: The consultant of the Bukit Kukus Paired Road project...


Action taken over irregularities at Bukit Kukus paired road project Penang

https://youtu.be/dMF95t2gXzg
Malaysia’s Penang Island has undergone massive development since the 1960s, a process that continues today with plans for transit and land-...

 

Huge landslide in Tg Bungah hill


Becoming bald: A view of the clearing work seen at Bukit Relau which was visible from the Penang Bridge in November last year. GEORGE..



 Fake Awards Scam for Penang Island City Council, Seberang Perai Municipal Council ! 
Home locked by Penang City Council over RM468 paltry arrears of assessment 

Penang floods and landslides, looking beyound natural causes! Seeking solutions: Penang Forum member and soil expert Dr Kam Suan Pheng giving her views during the dialogue session themed ‘Penang Fl..

https://youtu.be/ooyXvqmxbvw GEORGE TOWN: Some 20 houses located on a slope in Hong Seng Estate in Mount Erskine were flooded due


How to measure a politician?
Use technology to learn more about them before casting your vote Cheah taking a wefie with Tanjung Bungah assemblyman Teh Yee Cheu (be...

 Wanted: Leaders who listen !
Turning a blind eye: The grumblings over exposed hills are growing louder but little is being done to rectify the situation   G...


  With the GE imminent, politicians are already snarling at each other, hoping to score points early. I love dogs. I’ve always had o...



It’s hard to deny when the effects of climate change are all around us  Andrew Sheng says that from increasingly intense hurricanes t...


Why did MBPP approve the Tanjung Bungah development project? Read more at https://www.malaysiakini.com/letters/399357#qbRd534yu1JfC551....


https://youtu.be/kslhytLg-Wc Hills, landslides and floods: What to do?   The mega floods in Penang which followed the landslide...



Choong (in white) surveying the deforested hillslope next to Majestic Heights. PENANG MCA has raised concerns about the safety of the r...


Wet, wet woes: (Above) Bukit Jambul is flooded once again after an evening downpour. Firemen installing a pump to draw floodwater...


Council should not bow to development or political pressure, says city councilor, Khoo ‘Politicians should be ‘wakil rakyat’ and n...
(From left) Dr Kam will deliver a talk on ‘Understanding the Causes of Floods and Seeking Solutions. State assemblymen expressing inter...


https://youtu.be/4qaOB1n5tgA GEORGE TOWN: The Penang Island City Council has lodged a police report against the consultant of the aff...


Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ..


https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto's blog showing an active s..



Some representatives of the 24 residents associations and management corporations showing messages urging the state to resolve the flood...


Our Environment is Our Life - YouTube THE year has barely started, and already we have so many reports of weather and climate-related e...
Sponge City: Solutions for China's Thirsty & Flooded cities  China's 'sponge city' projects may be worthwhile examp...

Getting titles right in the engineering field in Malaysia

  Getting titles right in the engineering field in Malaysia ..

RECENTLY, the Institution of Engineers Malaysia (IEM) received an enquiry on the usage of the title “Engr.” for members of the institution. The title “Ir” was first introduced by IEM in the early 1970s for both the graduate and corporate members of the Inst...Getting titles right in the engineering field in Malaysia rightwaystosuccess.blogspot.com

 2 structures collapse due to incompetent engineers and irresponsible officer of MPPP/MBPP

 

 Penang has acknowledged the Hills Clearing cases reported by Penang Forum

 

Penang Forum tells Chief Minister: the unmitigated disasters on hill projects 


Wall and awning collapsed in house near construction site







Penang Island City Council, MBPP councilor Dr Lim fed up change not happening in Penang

 

Penang Forum concerns over hill clearing and floods; the Declaration & Recommendation 

 

 Penang flood aftermath: design pump system needed to drain out water, fix funding snag ...


  Long and winding road: This satellite picture from Google Earth Pro shows five planned interchanges of the Teluk Bahang-Tanjung Bun...



Humans Are Destroying the Environment   PETALING JAYA: They are supposed to be guardians of the environment, and yet “certain enforcem...


LATELY, we have been seeing many photographs and a lot of video footage of handcuffed men and women in orange T-shirts bearing the wor...




IJM and Genting excluded from investments wealth fund due to severe environmental damage
Environmental issues: IJM and Genting have interests in palm oil operations. Norwegian fund to call off investments on environmental iss...


PETALING JAYA: Some RM40mil from the Skills Development Fund Corp is believed to have been siphoned off by those tasked with utilising it.



Taiwan developer detained over deadly quake building collapse ...

The developer of a building in Taiwan that partially collapsed during an earthquake has been detained for negligent manslaughter with prosecutors saying the man was not licensed to oversee construction projects. The lower floors of the 12-storey Yun Tsui residential building which also housed a restaurant and hotel pancaked when a 6.4-magnitude quake struck the tourist hotspot of Hualien on February 6. A total of 17 people died across the eastern coastal town, 14 of them in the...

Getting titles right in the engineering field in Malaysia