Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.
Approximate Coordinates : 5°20'38.47"N,100°16'52.82"E
Reported in August 2016. Photos taken in November 2016 and 2014 by Penang Forum
PHW Report
Clearing and construction for a condo and semi-detached housing
project, Trehaus, reported in http://anilnetto.com/ 26 Aug 2016. Photo
taken in 2014 ...
Sources: Penang Hills Watch (PHW) | Penang Forum
Hill clearing activity by IJM Trehaus Project
Clearing and construction for a condo and semi-detached housing project, Trehaus, reported in http://anilnetto.com/ 26 Aug 2016. Photo taken in 2014 ... |
IJM sign-boards |
Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.
Two invalid pipe culverts formed sinkholes at BJ Cove houses
The invalid underground pipe culvert from the IJM Trehaus project directly converged at BJ Cove houses from another invalid underground pipe culvert from a nearby pond were burst, caused soil erosion, house slabs collapsed, multiple wall cracks, PBA water pipe burst, floods, sinkholes (by two pipe culverts converged in red) and damaged to BJ Cove houses due to blockages of waters whenever rains and because of lack of drainage system there. The sinkhole which later converted into a manhole by IJM, is a clear sign of soil erosion under the ground.
Therefore, damages to houses were caused by severe soil erosion due to water movement under the road and buildings.
The following shows the invalid underground pipe culvert from the IJM Trehaus site behind BJ Cove houses at Lintang Bukit Jambul 1:
IJM Underground Pipe Culvert to BJ Cove houses 2018 |
Waters rising from the IJM Pipe Culvert behind BJ Cove houses 2018 |
Waters are flowing back from another pipe culvert at IJM site to BJ Cove houses 2018 |
IJM Underground Pipe Culvert at bottom to BJ Cove houses 2018 |
IJM modifying/constructing their underground pipe Culvert in 2014 to BJ Cove Houses |
Waters gushing down from IJM Trehaus site to BJ Cove houses:
Waters gushing down from IJM Trehaus site to BJ Cove houses | |||
The nearby pond besides IJM Trehaus site:
IJM Hill cutting and hill Clearing 2014 |
Serious Drainage Issues
The Department of Irrigation and Drainage (DID or JPS) has just started in September 2017 constructing the drain from the pond to divert waters:
A drain under construction by JPS to divert waters from the nearby pond |
Letter from Penang Dept of Irrigation and Drainage (DID or JPS) in 2015 blamed IJM failure to comply with sedement control plan (ESCP) when its Trehaus started in 2014.
Clearly, the underground pipe culverts leaked and waters seeped through the ground and multiple cracks, as it did not happen immediately but over a period of time!
Developers dishonored directives/letters issued by Penang City Council (MBPP - Majlis Perbandaran Pulau Pinang) in 2015 to rectify the damaged house
Developers have not completed their committments to rectify the damages despite acknowledged their liability as per letters from Worldwide Venture Sdn Bhd, an subsidiary of IJM Land since 2014!
Despite the underground pipe culverts declared invalid by JPS and the Penang City Council's (Majlis Perbandaran Pulau Pinang, i.e. MBPP) issued stop work orders directing the developers, Worldwide Venture Sdn Bhd, a subsidiary of IJM Land to rectify the damages within 1 and 2 weeks time since 2015 (as per the above attached letters), the multiple wall cracks, slabs collapsed, PBA water pipes burst, leakage charges, damaging ceiling, electrical DB board, and tiles fallen, broken/popped up, are still pending settlement and remedial works to be carried out by parties responsible for the damages since 2014 !!
IJM Land only started in December 2017 constructing new drainage to divert waters from Trehaus Site to the pond and underground pipe culverts:
Pictures show IJM only started in December 2017 constructing drainage system to divert waters to the nearby pond and underground pipe culverts
Waters are flowing back to the pond during heavy rain 2018 |
Waters from IJM site overflown to the pond 2018 |
For waters to flow out smoothly, the pond must level up with more soils, 2018 |
Waters in the pond gone up during heavy rain 2018 - must build a wall to prevent waters from seeping thru houses. |
Waters cannot move out smoothly due to obstructions which are being removed by a man 2018 |
It is important that the pond should be made a dried pond instead of existing wet pond on the following reasons:
i) The area was originally a natural river/stream where waters will still be naturally running, seeped through underground even when the underground culverts are to be closed/abandoned later.
ii) More waters were being diverted from the IJM site to their underground pipe culvert and to BJ Cove houses.
iii) Now, drain waters from IJM site are being channeled back to IJM pipe culvert to BJ Cove houses at Lintang Bukit Jambul 1 where a manhole next to house no. 20 constructed by IJM is not closed despite it has been declared invalid and illegal by JPS! This poses concerns to residents at BJ Cove houses.
c |
IJM Drain water Pipe Culvert Site to BJ Cove houses |
IJM Drain water Pipe Culvert Site to BJ Cove houses |
Waters stuck behind BJ Cove houses at IJM site 2018 |
IJM Drain waters gushing down to pipe culvert |
Sinkhole at house 20 is covered up by IJM's underground pipe culvert from IJM Trehaus |
The damaged houses are still pending, not being completely rectified to date !
Damages appeared after IJM began construction works in 2014, like hill clearing, rock-blasting, piling and digging culvert at Trehaus site. As a result, sinkholes appeared, floods, waters seepage through multiple cracks on the ground, walls, tiles fallen from roofs and popped up from the ground due to vibration from rock-blasting and piling works.
Sinkhole converted to manholes (2 in cycles) at BJ Cove houses are visible from the top of IJM Trehasu site
Pictures showing floods, sinkholes at Lintang Bukit Jambul 1, 11900 Penang, damaged to BJ Cove houses, cracks, waters leakages seeped through the cracks, slabs collapsed, ceilings & tiles broken & fallen, electrical DB board explosion, etc caused by severe soil erosion due to water movement under the road and buildings. The underground pipe leaked and waters seeped through the cracks!
A big Sinkhole near BJ Cove house no. 20 |
IJM converted the sinkhole into a manhole waters from their underground pipe culvert at Trehaus |
These are IJM Manhole converted from Sinkhole:
Sinkhole at house 20 is covered up by IJM's underground pipe culvert from IJM Trehaus |
IJM converting the Sinkhole into Manhole next to BJ Cove no. 20 |
Outside house drain and fence damaged by IJM during mitigation of Sinkhole |
A big Sinkhole occurred due to invalid underground pipes culverts choked near house no. 20 |
Waters at the underground pipe culverts flown out from the house No. 20 to outside drain |
Slabs collapsed due to cracks without compacted hardcore |
Roof top Ceiling Board fallen due to strong vibration caused by IJM rock-blasting works 2014 |
Electric DB Board explored due to burst pipe waters seeped thru the wiring. |
Waters leaked from the burst pipes entered into Bedrooms |
Plumbers repaired the broken water pipes |
Truth Be Told:
The truths be told, as echoed, reinforced and justified by recent events in Penang floods on 15th Sept 2017, Landslides in Tanjung Bungah on 21 October 2017, the storm on Nov 4 & 5 2017, floods again on Jan 5, 2018, and the Huge 'bleeding' landslide in Tg Bungah hill on May/June 2018 in related posts,
.... see more on links to following reports:
https://youtu.be/ooyXvqmxbvw GEORGE TOWN: Some 20 houses located on a slope in Hong Seng Estate in Mount Erskine were flooded dueHills, landslides, floods and damaged houses ...
Penang landslides & flooding are natural disasters man-made...
Penang floods and landslides, looking beyound natural causes!
Penang landslide, whose faults?
Penang Paya Terubong Residents living under shadow of fear!
Penang landslide tragedy, why it happened?
PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development
We demand immediate enforcement & Actions to complete the remedial works:
1. The parties responsible must quickly without further delays, without condition to settle the claims and start the remedial works to the damaged houses, as both JPS has declared underground pipe culverts invalid and MBPP has issued stop work orders directed the developers, Worldwide Venture Sdn Bhd, a subsidiary of IJM Land to rectify the damages within 1 and 2 weeks time since 2015!
2. Enforce IJM's & MBPP' Letters/Stop-work Orders (attached in above), and divert waters from the two invalid underground pipe culverts deemed illegal at the IJM Trehaus site and nearby ponds which must be closed and grouted as a long term solution to the problems.
3. Enforce a fresh cease and desist to Stop Work of IJM Trehaus construction project until the structural damages to house at 20 Lintang Bukit Jambul 1, BJ Cove have been resolved and settled the claim for damages and distress caused by the fear and danger of living in the house, without further delays and their suffering more than four years since 2014. Repairs and remedial works must start promptly as more damages and suffering will fellow!
4. Beef up the enforcement and accountability not just in government agencies but also in professional bodies, like the Board Of Engineers Malaysia (BEM), the Institute of Engineers Malaysia (IEM), etc to uphold the professional ethics, integrity and standards, to ensure public safety of the buildings and people life.
5. The pond must be made a Dried pond for waters to flow out smoothly, because there was originally two natural rivers/streams in the area where waters will still be running/seeping through naturally under the ground.
6. Now, drain waters from IJM site are being channeled back their underground pipe culvert flowing to BJ Cove houses at Lintang Bukit Jambul 1 where a manhole next to house no. 20 constructed by IJM is not closed despite it has been declared invalid and illegal by JPS! This is a great concern to residents at BJ Cove houses. We want JPS and MPPP to close & grout the manhole promptly.
7. Damaged house owners firmly reserve all their rights to take all necessary legal steps against those responsible exclusion their liabilities.
Findings from Penang Forum
Dr Kam, a scientist, focused on expansion of impermeable surface area (caused by ill planned development and replacing natural ground cover such as hills, fields and trees that act as a water absorbing sponge) and soil erosion and landslides (caused by cutting and development in hill areas) as two factors that need special attention.
She quoted Datuk Kam U Tee, the Penang Water Authority general manager (1973~90), as having correctly explained the Penang floods of October 2008, as follows: the floods were caused by conversion of the Paya Terubong and Bayan Baru valleys into “concrete aprons that do not retain water. The water immediately flows into streams causing flash floods even with moderate rainfall. Because of hillcutting activities, the flowing water causes erosion of the slopes which carries mud and silt into the river beds”. ( The Star, Oct 24, 2008).
See more ....
Credits - Slides presented by Environmental, health and safety consultant Aziz Noor, and scientist Dr Kam Suan Pheng at the Penang Forum event on Oct 29, 2017
See more ....
Practise true CAT for Sustainable Development
Penang government must provide a COMPETENT flood mitigation plan for the state starting with a comprehensive Drainage Master Plan Study and not slogan.
The Penang government has to be ACCOUNTABLE to the people and not private developers. In other words, ‘Politicians should be ‘wakil rakyat’ and not ‘wakil pemaju’. If certain waterways and catchment areas have to be gazetted as permanent drainage and storage areas, then so be it.
The safety and well-being of the Rakyat has to come first. In the interest of TRANSPARENCY, Penang has to launch an inquiry into how the local council approved property developments on slopes without adequate slope protection.
1. Wanted: Leaders who listen !
2. Sustainable Development in Penang
3. Call to reassess Penang hillside projects, councillor addresses full council meeting of MBPP
4. Penang landslide, whose faults?
Related:
Include Penang Forum in panel probing Bukit Kukus landslide tragedy
At Penang landslide memorial, group questions silence of PH MPs
Consultant, contractor of Bukit Kukus paired road project slapped with ...
Risky building on hillslopes - Nation
Come together to save our state
In Malaysia, an island drowns in its own development
Watch "Slope Stability" on YouTube
https://youtu.be/2wT2he6Numk
Penang MP rapped for asking for allocation while rejecting Budget ...
KUALA LUMPUR: A Penang Opposition lawmaker was rapped for voting ... Budget 2018 yet seeking an allocation for flood mitigation projects.RM150mil for flood mitigation projects - The Star Online
A tempest flays the north
GEORGE TOWN: When the storm hit, everyone in the north prayed it would soon blow over.
Penang paralysed by floods - Nation
Irked residents to hold meeting with state representatives on Penang ...
https://youtu.be/n2vO-nsZxkY
'Bleeding' landslide worries residents - Nation
Damaged houses to be repaired - Metro News
Rep: Redevelop village to solve recurring erosion - Metro News
Residents prefer affected houses to be torn down manually
Bruised in sinkhole fall at home - Nation
Penang CM must stop blaming past govt for problems
Cracks in homes force seven Penang families to flee - Nation
Here's the proof — federal govt gave only RM443mil for flood mitigation
Former councillors claim Penang government abuse caused floods
PAS claims graft caused floods in Penang | Malaysia
Penang pays high price in storm havoc - Nation
Up to the chest in water, up to the neck with the excuses - Nation
Dept: Typhoon Doksuri caused erratic weather across Penang ...
Rapid development in Penang root cause of massive flash floods ...
Admit failure in solving floods and stop giving excuses, Penang govt told
Deluge brings chaos to northern states - Metro New
Penang floods: Body of missing woman found in Bukit Jambul river
Updated) Penang flash floods claim a life, second death due to floods ...
https://www.nst.com.my/.../updated-penang-flash-floods-claim-life-second-death-due-...
Boast to end floods rings hollow - Nation
Anti-flood plan in pipeline - Metro News
Chant: Set up unit to monitor hill projects - Nation
CAP: Halt projects in flood-prone areas until wet spell ends - Nation ...
Penang mayor Maimunah quits job to accept UN post
Hiking trail in awful condition - Metro News
Clogged drains main cause of floods - Metro News
Narrow drains contribute to flooding
The narrow drainage system which Chua claims results in flooding in the area.
Related posts:
Cracked drain causes road cave-in, house nearby on brink of callapse
https://youtu.be/9yXuW1pdrt4MBPP, contractor, engineers and DOSH named as responsible in fatal Penang landslide
Kudos to Deputy Chief Minister I Datuk Ahmad Zakiyuddin for holding the four parties accountable for the Bukit Kukus landslide
tragedy. The inquiry still begs a lot of questions, e.g. why was the
contract given to Yuta Maju from Terengganu? Could the accident have
been prevented if a proper EIA was done? It is not just a "bureaucratic
hurdle" but supposed to identify risks and advise mitigation. If the
authorities wish to go on with the project, it is not too late to
commissi...
See more
See more
“This is no simple incident as nine deaths resulted from it. Very stern action must be taken against the MBPP, and that includes strong disciplinary action against the mayor and officers responsible.
“Otherwise, it will be business-as-usual in the MBPP as the officers will be allowed to go scot-free with impunity.
freemalaysiatoday.com
Come together to save our state - Letters | The Star Online
Landslide nation, Malaysia ranks highly for landslides
A drone picture of the collapsed beams
along Jalan Tun Sardon leading to Balik Pulau on the left while Jalan
Paya Terubong on the ri...
Consultant gets show-cause letter for
‘overlooking hilltop stream’ GEORGE TOWN: The consultant of the Bukit
Kukus Paired Road project...
Action taken over irregularities at Bukit Kukus paired road project Penang
Malaysia’s Penang Island has undergone
massive development since the 1960s, a process that continues today with
plans for transit and land-...
Huge landslide in Tg Bungah hill
Penang floods and landslides, looking beyound natural causes! Seeking solutions: Penang Forum member and soil expert Dr Kam Suan Pheng giving her views during the dialogue session themed ‘Penang Fl..
https://youtu.be/ooyXvqmxbvw GEORGE TOWN: Some 20 houses located on a slope in Hong Seng Estate in Mount Erskine were flooded due
How to measure a politician?
Use technology to learn more about them before casting your vote Cheah taking a wefie with Tanjung Bungah assemblyman Teh Yee Cheu (be...
Wanted: Leaders who listen !
Turning a blind eye: The grumblings over
exposed hills are growing louder but little is being done to rectify the
situation G...
With the GE imminent, politicians are
already snarling at each other, hoping to score points early. I love
dogs. I’ve always had o...
It’s hard to deny when the effects of
climate change are all around us Andrew Sheng says that from
increasingly intense hurricanes t...
Why did MBPP approve the Tanjung Bungah development project? Read more at https://www.malaysiakini.com/letters/399357#qbRd534yu1JfC551....
https://youtu.be/kslhytLg-Wc Hills, landslides and floods: What to do? The mega floods in Penang which followed the landslide...
Choong (in white) surveying the deforested
hillslope next to Majestic Heights. PENANG MCA has raised concerns
about the safety of the r...
Wet, wet woes: (Above) Bukit Jambul is
flooded once again after an evening downpour. Firemen installing
a pump to draw floodwater...
Council should not bow to development or
political pressure, says city councilor, Khoo ‘Politicians should
be ‘wakil rakyat’ and n...
(From left) Dr Kam will deliver a talk on
‘Understanding the Causes of Floods and Seeking Solutions. State
assemblymen expressing inter...
https://youtu.be/4qaOB1n5tgA GEORGE TOWN: The Penang Island City Council has lodged a police report against the consultant of the aff...
Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ..
https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto's blog showing an active s..
Some representatives of the 24 residents
associations and management corporations showing messages urging the
state to resolve the flood...
Our Environment is Our Life - YouTube THE
year has barely started, and already we have so many reports of weather
and climate-related e...
Sponge City: Solutions for China's Thirsty & Flooded cities China's 'sponge city' projects may be worthwhile examp...
No comments:
Post a Comment