Friday, 26 January 2018

Penang Landslide occured days after remedial works started

Cracks at Tanjung Bungah site began in June, Commissioner of Inquiry told

Expert panel: (From right) Yeo, Dr Gue and Prof Ramli arriving for the inquiry.
 
GEORGE TOWN: A temporary structure supporting a worksite slope in Tanjung Bungah developed cracks in mid-June, a Commissioner of Inquiry heard.

Soil Mechanic Sdn Bhd director Cheah Wing How, who was a sub-contractor of the project where a landslide killed 11 workers, said he was informed by a clerk to carry out remedial works as the granite wall had cracked.

Cheah said his team left after completing the granite works and soil-nailing works to enhance the stability of the temporary slope.

There was, however, no mention when they completed the works.

“When we returned, we found there were pile cap excavation works carried out near the slope.

“We believe there was soil movement that resulted in the cracks on the granite wall.

“We were carrying out remedial works and 11 days into the job, the landslide happened,” said Cheah, who has 20 years’ experience in the field.

Cheah was testifying on the first day of the public hearing into the landslide tragedy by the State Commission of Inquiry (SCI) at City Hall in Esplanade yesterday.

On Oct 21, last year, a landslide hit the affordable condominium project made up of two 49-storey towers with 980 units in total within the Permai Village township near the Tunku Abdul Rahman University College.

Among the 11 killed was site supervisor Yuan Kuok Wern, 27.

During the proceeding, the Penang Island City Council (MBPP) also presented eight drone videos that showed the slope and the surrounding area after the tragic incident.

SCI chairman Datuk Yeo Yong Poh said they planned to carry out a site visit tomorrow.

He also fixed the hearing to continue until Monday, followed by Feb 8 to Feb 11, March 24 to March 28 and April 18 to 25.

Other members of the commission are geotechnical expert Datuk Dr Gue See Sew and forensic geo-technical engineer from Universiti Teknologi Malaysia Prof Ramli Nazir.

The SCI was gazetted on Dec 21 last year to investigate the landslide after Yang di-Pertua Negri Tun Rahman Abbas gave his consent on Dec 6, 2017, for the appointment of the members of the commission and its terms of reference.

Meanwhile, Penang Citizens Awareness Chant Group (Chant) adviser Yan Lee said the entrance to the Teik Granite Quarry, which is located near the site where the landslide occurred, should be fenced up.

“Anyone can just walk into the site as the safety measure is not up to mark.

“We have voiced our concern to the Penang Island City Council, the Department of Environment as well as the Land and Mines Department,” he said yesterday.

By Chong Kah Yuan and Jo-Leen Wong The Star


Related Links:

Boulders slid down hill prior to disaster - Nation





Contractors in jitters over temporary slopes - Nation


Related posts:

Penang landslide tragedy, plea went unheeded, no one listened !

 

Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'..

Tuesday, 25 July 2017

The stalled building defects causing delays of relocation ..

Not ready: (Clockwise from top) The front view of the Batu Ferringhi market in Penang, exposed electrical sockets and cracked floor in the badminton court, and a leaking pipe in the washroom.


Defects causing delay of move to RM9mil Batu Ferringhi market


The scheduled relocation of traders to the RM9mil Batu Ferringhi market on Aug 14 is postponed to a later date until shortcomings such as leakage in the washrooms and cracks on the floor are fixed.

Lim checking on the condition of the market.- Photos: ZHAFARAN NASIB/The Star

SENIOR officers of the Penang Island City Council (MBPP) were left red-faced after Chief Minister Lim Guan Eng spotted several defects in the almost completed RM9mil Batu Ferringhi market during a site visit.

Lim, who was irked with the shortcomings, asked his officers to collect back copies of his text speech given earlier to reporters.

“Before I came in, I went to the washroom. I thought it would be ready.

“But the male washroom was locked and I had to use the unoccupied ladies washroom instead.

“If the market is considered ready (by the council), then it is unacceptable,” he said.

Washroom with missing taps

 
A leaking pipe pipe in the washroom

It is learnt that the ladies washroom was leaking and some of the taps had yet to be fixed.

Lim, who was walking to the dining area, was stopped by several traders who requested the council delay their relocation into the market which was earlier scheduled on Aug 14.

Speaking to newsmen, Lim said another date would be set.

“We cannot fix a date now until we are satisfied that the shortcomings have been rectified,” he said.

MBPP mayor Datuk Maimunah Mohd Sharif said she would hold discussions with the market contractor and architect.

“Cracks have also appeared on the floor of the badminton courts,” she said.


Maimunah said the council had issued the Certificate of Practical Completion (CPC) for the market but not the Certificate of Completion and Compliance (CCC).

The market was scheduled for completion by the end of last year.

There are 16 hawker stalls, 28 wet and dry market units, a multipurpose hall, a library, three badminton courts, playground, bicycle path, shower rooms and 90 parking bays.

Source: The Star/ANN by Intan Amalina Mohd Ali

Related Link:

Residents: Removed plants were well maintained - Community 

Related posts:

Wall and awning collapsed in house near construction site 

 

Errant hill clearing by developers causes of flood, sinkholes, seepages damaged houses!

Saturday, 13 December 2014

Homes are cracking !



PENGERANG: Dozens of residents who were relocated due to the development of the Refinery and Petrochemical Integrated Development (Rapid) expressed disappointment over the poor workmanship of their new homes in Taman Bayu Damai.

They are upset that their houses, which are less than a year old, have already started cracking, with some wide enough for fingers to go through.

They blamed this on soil movement.

“The foundation for many of the houses have started to slip, causing huge holes to appear below our single-storey bungalow,” said retiree Lukiman Sastaro.

The 67-year-old, who moved from Sg Kapal, said his house was among the worst hit.

“I got over RM300,000 in compensation and used RM105,000 to buy this house. The rest went into renovations,” he said, adding that he was now having sleepless nights.

“Even my driveway sank by several centimetres,” said Lukiman.

Another resident, Sia Pek Im, 61, said she was worried about the safety of her two grandchildren after huge cracks appeared in her kitchen.

“But I have nowhere else to go,” she said.

Another, Hamidon Ahmad, said he, too, suspected that there was soil movement and that the developer had not carried out proper mitigation works before building the houses.

“I decided to carry out repair works on my own as I am worried for my family’s safety,” said the 56-year-old.

“Even my relatives’ home next door is affected. The relevant agencies should check if the houses have met the safety criteria before the Certificate of Fitness is issued,” he said, adding that the site used to be a swamp.

Kota Tinggi district officer Mohd Noorazam Osman confirmed that it was a geological problem due to earth movement.

“We are working with the state Economic Planning Unit (Upen), which is in charge of the project to remedy this,” he said.

“Residents’ safety is our main concern and houses that are badly damaged will be demolished,” he said, adding that it was up to Upen to decide what action should be taken against the developer or contractor.

State Upen director A. Rahim Nin said the Johor government had appointed a private contractor under the design-and-build concept for the 631 houses in the area.

“So far, 555 units have been given to residents who were relocated from Kg Sungai Kapal, Kampung Langkah Baik and Kampung Teluk Empang,” he said.

“We have directed the contractor to repair the defects – as based on our agreement with them. The defect liability period is two years,” he said, adding that 67% of the complaints had been addressed so far.

By Nelson Benjamin The Star/Asia News Network