Share This

Showing posts with label Contractors. Show all posts
Showing posts with label Contractors. Show all posts

Thursday, 14 February 2019

MBPP, contractor, engineers and DOSH named as responsible in fatal Penang landslide

https://youtu.be/R07RRPADcK0

https://www.thestar.com.my/news/nation/2019/02/14/landslide-report-blames-contractor-mbpp-and-dosh/?jwsource=cl

Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer. NSTP/MIKAIL ONG
MBPP among four named as responsible in fatal Penang landslide

GEORGE TOWN: Four parties have been identified as being responsible for the fatal landslide at the construction site of the paired road at Jalan Bukit Kukus last October incident, including the Penang Island City Council (MBPP).

A special investigation committee set up by the Penang government following the fatal landslide at the construction site also named the other three parties, namely the contractor Yuta Maju Sdn Bhd, the consultant, Jurutera Perunding GEA (M) Sdn Bhd and the independent checking engineer G&P Professional Sdn Bhd.

Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer.

“By appointing Jurutera Perunding GEA, it does not mean that the council is free from responsibilities to ensure the success of the project from all aspects.

"As such, any actions to be taken against the council will depend on the outcome of investigations by the police, the Department of Occupational Safety and Heath (DOSH) and the Construction Industry Development Board (CIDB) into the incident," he said when making public findings of the investigation committee.

Ahmad Zakiyuddin said as for Yuta Maju, it had failed to ensure satisfactory mitigation works at the project site, and that the temporary slope constructed at the project site was not endorsed or designed by accredited consultants, which was a violation of the Board of Engineers Malaysia (BEM) guidelines.

“It also failed to ensure site safety by removing the empty containers at the project site, where nine bodies were recovered," he added.

As for Jurutera Perunding GEA, Ahmad Zakiyuddin said the party had failed to ensure that the contractor abide by the guidelines set out by the BEM, while G&P Professional had failed to abide by the job scope given by the council.

“Following our findings, we have recommended that the contractor, consultant and independent checking engineer be blacklisted from any tender consideration for projects in the future.

“That said, they will still have to continue their works for the paired road project, until the project completion, slated for May next year,” he added.

The landslide at the Bukit Kukus paired roads project site on Oct 19 last year killed nine site workers and left four others injured.

The search and rescue (SAR) operation was called off after five days. The project's stop-work orders, separately issued by DOSH, CIDB and the council, were lifted up recently.

Ahmad Zakiyuddin said the special investigation committee also identified 10 main factors which had contributed the to fatal landslide, particularly not fully adopting best practices in construction work.

Other factors included:

* heavy rain on the morning of the incident at 55mm

* the contractor was unable to enter the project site to carry out mitigation works as stop-work order was issued by DOSH two days prior to the incident following a worksite accident

* unsafe construction processes

* failure to recognise the significance of an earlier incident (falling beams at another part of the project site two days prior to the landslide);

* lack of supervision

* failure to identify risk due to the change of process

* lack of comprehensive inspection and testing

* failure in risk communication

* poor management of sub-contractors.

Asked on why the services of the contractor, consultant and independent checking engineer were not immediately terminated following the incident, Ahmad Zakiyuddin said from what he understood, the stop-work orders issued on the three were only for one part of the project and not the entire project.

"Also, there was no record of safety issues prior to the landslide," he said.

He called on efforts to protect the remaining part of the project as a resu

lt of a negative perception.

"Any delay will put the project at greater risks."

To another question if the special investigation committee's findings would be made public, he there had been no plans to do so as the report served as a guideline for the state. - By Audrey Dermawan, NST >


‘MBPP hired resident engineer for Bukit Kukus project’

GEORGE TOWN: The Penang Island City Council (MBPP) appointed a resident engineer and an independent checking engineer even before the start of the Bukit Kukus paired road project, says Chief Minister Chow Kon Yeow.

“If you see the action taken by MBPP, they understand their technical insufficiency in terms of a geotechnical engineer. That’s why in the contract, they required the main contractor to appoint a resident engineer, who was paid by MBPP to monitor the project on MBPP’s behalf.

“The independent checking engineers were also paid by MBPP. So, it was a measure taken by MBPP even before the start of the project, knowing that this is a big project.

“They did not have the capacity to monitor the project as they have only two or three engineers who have to be looking at other matters besides this project.

“So, they took action to appoint a resident engineer as well as independent checking enginners to act on behalf of MBPP,” he told reporters at the Penang Development Corp­oration Chinese New Year celebration at the PDC office in Bayan Lepas yesterday.

Chow also said the state would wait for the Department of Occupational Safety and Health (DOSH) report first.

“We will leave it to DOSH’s findings. Let DOSH come out with the report and we will take the necessary action after that,” he said.

Asked if MBPP had to bear necessary compensation for families of the victims of the landslide last October, Chow said MBPP had not received any claim so far.

Chow was asked to respond to the Con­sumers Association of Penang’s (CAP) call for stern action to be taken against the wrongdoers responsible for the tragedy.

CAP president S.M. Mohamed Idris in a statement yesterday said: “While we welcome the investigation committee’s findings as to who is responsible for the tragedy, we are concerned that apart from recommending the blacklisting of the contractor, consultant and independent checking engineer from any tender consideration for future projects, it appears that no further stern action has been recommended.

“In particular, we want to know what action will be taken against MBPP,” he said.

Deputy Chief Minister I Datuk Ahmad Zaki­yuddin Abdul Rahman, who headed the investigation panel, was reported yesterday as saying that MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired road project had not adhered to construction and engineering best practices.

Meanwhile, MBPP acknowledged responsibility for the Bukit Kukus landslide tragedy as it is the council’s project.

MBPP mayor Datuk Yew Tung Seang said the council was not pushing away any responsibility or negative comments on the council and project, and that it would be taken seriously. - By Cavina Lim and Intan Amalina Mohd Ali, The Star

Penang landslide report blames contractor, MBPP and DOSH

The special investigative panel report on the Bukit Kukus landslide had not been made public, but excerpts of the findings were made available by the state.

However, it has raised more questions than answers as the state blamed the contractor, Penang Island City Council (MBPP) and the Department of Occupational Safety and Health (DOSH).

In an immediate response, DOSH Penang director Jaafar Leman denied the department was to be blamed for the landslide.

“We were not even invited to be part of the investigative panel to give our views. How could we be blamed?” he asked.

According to the statement by Deputy Chief Minister 1 Datuk Ahmad Zakiyuddin Abdul Rahman who headed the investigative panel, the stop-work order on Oct 17 prevented contractors from entering the site to do maintenance works.

As a result, the temporary toe drain overflowed and water was retained on the reclaimed land contributing to the collapse of the slopes.

“How could a stop order which was issued on Oct 17 contribute to the landslide which occurred on Oct 19?” asked Jaafar.

He said the slopes would have been risky from the beginning as the contractor did not do any mitigation works to strengthen them and it does not make sense to blame DOSH.

The stop-work order was issued on Oct 17 after 14 beams fell in a ravine.

Earlier, during a press conference, Ahmad Zakiyuddin said MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired roads project, had not adhered to construction and engineering best practices.

“The landslide was caused by many factors, which included a temporary construction of a platform to place machinery which was not constructed properly. The temporary platform was created to allow heavy vehicles lift beams for the paired road project.

“MBPP, as owners of the project, had failed to ensure all the hired parties carried out their job.

“MBPP had failed to hire a professional engineer for temporary works to design and supervise the site,” he said yesterday.

Ahmad Zakiyuddin said another factor was the downpour in the morning of the day of the landslide.- The Star


Related News

Kudos to Deputy Chief Minister I Datuk Ahmad Zakiyuddin for holding the four parties accountable for the Bukit Kukus landslide tragedy. The inquiry still begs a lot of questions, e.g. why was the contract given to Yuta Maju from Terengganu? Could the accident have been prevented if a proper EIA was done? It is not just a "bureaucratic hurdle" but supposed to identify risks and advise mitigation. If the authorities wish to go on with the project, it is not too late to commissi...
See more

 “This is no simple incident as nine deaths resulted from it. Very stern action must be taken against the MBPP, and that includes strong disciplinary action against the mayor and officers responsible.

“Otherwise, it will be business-as-usual in the MBPP as the officers will be allowed to go scot-free with impunity.
Metro News14 Jan 2019


Bukit Kukus road project illegal, says consumer group | Free Malaysia ..

 

Penang blacklists contractor, engineers in Bukit Kukus road project ...

 

Groups demand Penang govt release Bukit Kukus landslide probe ...

 

Bukit Kukus project to proceed with extra caution - Nation



Related Posts:

Action taken over irregularities at Bukit Kukus paired road project Penang

 

Soil erosion mitigation plans ignored, waters from stream identified as main cause !

 

Penang Landslide occured days after remedial works started

 

Penang landslides & flooding are natural disasters man-made?

 

 Call for action on flooding solution

 

Structural defects to blame, stop history repeating itself !

 

 Fake Awards Scam for Penang Island City Council, Seberang Perai Municipal Council !

 
Dubious honours: (Above) Former Penang Island City Council mayor Patahiyah Ismail with the trophy and certificate for Best Municipal Manager awards in 2013 while her Seberang Prai counterpart Maimunah (pictured here with the Chief Minister Lim Guan Eng and his aide Wong Hon Wai) received the same latter award in 2014

  Malaysian Public varsities, companies, GLC execs also recipients of EBA fake awards

 

Thursday, 25 October 2018

Action taken over irregularities at Bukit Kukus paired road project Penang

https://youtu.be/dMF95t2gXzg

Special task force formed to probe landslide


GEORGE TOWN: The state government has formed a special investigative committee to probe the landslide at the Bukit Kukus Paired Road construction site in Paya Terubong.

Chief Minister Chow Kon Yeow said preliminary reports by the Penang Island City Council (MBPP) and the Drainage and Irrigation Department showed there were elements of non-compliance in construction procedures carried out at the site.

He said the committee would be led by Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, with State Public Works, Utilities and Flood Mitigation Committee chairman Zairil Khir Johari as a member and an engineer from the state secretary’s office.

“Relevant agencies, contractors, sub-contractors and independent checking engineers involved in the project will be questioned,” he said during a press conference in his office at Komtar yesterday.

Chow said this was a separate investigation from the compulsory investigations carried out by the Department of Occupational Safety and Health and Construction Industry Development Board among other relevant agencies.

Once investigations are complete, Chow said the findings would be brought to the Board of Engineers Malaysia, an agency under the Works Ministry that monitors and regulates engineers.

“MBPP is not involved in the investigation as it is the project owner,” said Chow.

Action taken over irregularities at paired road project, says Zairil


A special task force detected several irregularities when conducting spot checks at the Bukit Kukus Paired Road project site earlier this month.

State Works, Utilities and Flood Mitigation Committee chairman Zairil Khir Johari said the task force, formed under the Erosion and Sedimentation Control Committee (Ops Lumpur), was to check for compliance under the Erosion and Sedimentation Control Plan (ESCP).

“On Oct 8, a team led by the Drainage and Irrigation Department found sediments in a pond and irregularities in the check dams.

“The stockpiles were not maintained well and could affect the flow of Sungai Relau during heavy rain, causing mud floods, he told reporters in Komtar yesterday.

Zairil said as per the standard operating procedure, the Ops Lumpur team issued a letter to the consultant of the project, demanding that mitigation measures be taken within 14 days.

“On Oct 12, the findings of Ops Lumpur were reported to the Erosion and Sedimentation Control Committee and the next day, an initial stop-work order was issued by the Department of Occupational Safety and Health (DOSH) following the beam collapse.

“A full stop-work order was issued by DOSH on Oct 17,” he said.

Zairil said on Sept 28, his office received a report on the concerns over hill-clearing activities in Penang from the Penang Hills Watch, and replied to them on Oct 4.

“I was concerned about the complaints, as erosion and sedimentation would indeed cause bottlenecks in the rivers downstream, especially during the rainy season.

“Claims that the complaints were not attended to are untrue. In fact, action was taken immediately,” he said adding, “The cause of the Bukit Kukus landslide must be uncovered.”

Separately, Zairil said 17 slopes in the state were under repair and RM10mil had just been approved by the state government. - The Star

Giant pillars a reminder of Bukit Kukus tragedy

Impossible to ignore : The large concrete pillars that remain standing at the Bukit Kukus landslide site in Paya Terubong.

GEORGE TOWN: A row of giant concrete pillars soaring high into the sky serves as a reminder of the landslide tragedy which claimed nine lives at the Bukit Kukus Paired Road project in Paya Terubong.

The tallest of them stands at about 20 storeys and remains perched between the hills where soil erosion brought down 13 containers housing the ill-fated foreign workers last Friday.

Before the Department of Occupational Safety and Health Department (DOSH) gives the all clear for the project to resume, most of the workers at the site have remained while a few moved out to look for temporary work.

A Bangladeshi worker who declined to be named was seen carrying a cardboard box containing his personal belongings to another construction site nearby.

“The boss said there is no more work here, so I contacted my friend who recommended me for another job. I will be staying at his place.

“Once this project resumes, I shall come back,” the 30-year-old said.

At the site, rubble was scattered all over the 9,290 sq m site with the 13 green containers salvaged by cranes left in a corner.

The last foreign worker to be found was 33-year-old Bangladeshi Mohamad Uzzaal. He was pinned under a container and rescuers had to dig 10m to extricate the body.

At the height of the ops, two cadaver dogs were despatched to the scene to search for bodies while two other sniffer dogs were there to locate survivors.

A small open area beside a farm further up the hill above the site where photographers and videographers camped for five days to capture the ongoing rescue operation remains cordoned off.

On Monday, the media was taken on a tour of the site after the search and rescue operation, involving over 100 rescue personnel, was called off.

The water in the stream, which looked like teh tarik on Friday, was crystal clear now after its flow on top of the hill was diverted.

Even as the ops ended and all the missing foreign workers had been located, residents living nearby raised their concerns over the project.

Technician Tan Keng Wee, 36, hoped that the project would continue since most of it had already been done, but wanted better safety measures in place at the site.

“The traffic in Paya Terubong during peak hours is chaotic due to the narrow road passing by the hills. We need the new elevated road bypass but please make sure it is safe,” he said.

Food stall operator Mohd Subri Noor, 52, also shared his concern.

“I’m worried as many landslides have happened here. Many of them could have been prevented,” he said.

The RM530mil alternative road linking Lebuhraya Thean Teik in Bandar Baru Air Itam to Lebuh Bukit Jambul began in January 2016.- The Star


Related:   


Include Penang Forum in panel probing Bukit Kukus landslide tragedy

 

  At Penang landslide memorial, group questions silence of PH MPs

Consultant, contractor of Bukit Kukus paired road project slapped with ...


Risky building on hillslopes - Nation


Related posts:


Consultant gets show-cause letter for ‘overlooking hilltop stream’ GEORGE TOWN: The consultant of the Bukit Kukus Paired Road project...
A drone picture of the collapsed beams along Jalan Tun Sardon leading to Balik Pulau on the left while Jalan Paya Terubong on the ri...
Precarious situation: The collapsed beams along Jalan Tun Sardon which fell and broke after being knocked down. https://www.thestar.c...

Monday, 15 October 2018

Bukit Kukus paired road hits snag before mishap, stop work order to contractor on collapsed beams

Precarious situation: The collapsed beams along Jalan Tun Sardon which fell and broke after being knocked down.

https://www.thestar.com.my/news/nation/2018/10/14/stop-work-road-contractor-told-dosh-to-look-at-work-sites-procedures-after-mishap/?jwsource=twi

Stop work, road contractor told


BALIK PULAU: The contractor of the 600m elevated road project linking Jalan Bukit Kukus to Jalan Tun Sardon here has been issued with a stop-work order.

The order came following a mishap on the site where 14 concrete beams measuring 25m each fell onto a slope in Jalan Tun Sardon on Thursday.

Eleven beams broke apart in the 8.30pm incident. However, no injuries were reported.

It is learnt that a crane operator accidentally knocked down one of the beams laid on the ground, causing others to fall onto the slope like dominoes.

Penang Department of Occupa­tional Safety and Health (DOSH) director Mohd Rosdee Yaacob said the contractor had been instructed to be present at the DOSH office tomorrow for a meeting.

“We are reviewing the standard operating procedures at the work site.

“For now, the contractor is not allowed to load and unload other concrete beams,” he said yesterday

Mohd Rosdee said his officers were only sent to the site on Friday as they were not immediately informed of the incident.

State Works Committee chairman Zairil Khir Johari said the contractor had been told to prepare a full report for DOSH.

He said the Penang Island City Council (MBPP) would also initiate an internal inquiry tomorrow.

The construction of the elevated road, together with the upgrading of a 1.1km stretch along Lebuhraya Thean Teik and a 1.5km stretch along Lebuh Bukit Jambul, is a MBPP project costing RM275.6mil and is scheduled for completion early next year.

The three segments are part of the project for the construction of the RM545mil alternative road – Jalan Bukit Kukus – to help ease traffic snarls along Jalan Paya Terubong, which is an arterial road linking Bayan Baru, Balik Pulau and Air Itam.

The construction works involve linking Lebuhraya Thean Teik in Bandar Baru Air Itam and Lebuh Bukit Jambul in Penang via Jalan Bukit Kukus, building an elevated U-turn along Lebuh Bukit Jambul for those who want to make a turn and go back to Relau. - The Star

Paired road already hits snag

Slow path ahead: The elevated road near Jalan Paya Terubong in Penang will not be ready for another two years.
GEORGE TOWN: Work on the RM545mil Jalan Bukit Kukus paired road project has hit a snag even before the construction mishap in Jalan Tun Sardon.

The completion date on the project, an alternative road linking Lebuhraya Thean Teik in Bandar Baru Air Itam to Lebuh Bukit Jambul, will be delayed by a year till mid-2020 due to unforeseen obstacles during construction.

State Works, Utilities and Flood Mitigation committee chairman Zairil Khir Johari, in describing the project as “very complicated”, said it was constructed by three parties as a cost-saving measure.

“The Penang Island City Council (MBPP) will construct 2.8km of the stretch, while PLB Land Sdn Bhd and Geo Valley Sdn Bhd will construct the remaining 1.4km and 0.7km respectively,” he said.

Zairil said while the three parties involved in the works faced various issues resulting in the delay.

“For example, the MBPP which is working on the 2.8km stretch costing RM275.6mil, faced a delay due to land acquisition issues, realignment and relocation of cables.

“The project is 69% done and to be completed by early 2020.

“PLB Land faced issues with big rocks and boulders. The RM150mil section has progressed 36% and scheduled for mid-2020,” he said.

Zairil said that Geo Valley faced legal issues as the residents affected by their section of the project took up matters with the Appeals Board and the case was pending.

The RM120mil stretch by Geo Valley is now 18% completed.

“Once PLB and Geo Valley complete their portions, we will connect them accordingly,” he said.

It was earlier reported that the contractor of the 600m elevated road project linking Jalan Bukit Kukus to Jalan Tun Sardon was issued with a stop-work order.

The order came after a mishap on the site where 14 concrete beams measuring 25m fell onto a slope in Jalan Tun Sardon on Thursday. No injuries were reported.

It is learnt that a crane operator accidentally knocked down one of the beams laid on the ground, causing others to fall onto the slope.

Paya Terubong assemblyman Yeoh Soon Hin hopes that there will be no further delays.

“About 60,000 vehicles use Jalan Paya Terubong daily to get to Bayan Lepas, and traffic congestion is bad during peak hours.

“I hope the project will be completed safely according to specifications and on schedule for the people to use,” he said.

Once the alternative route is completed, traffic is expected to see a reduction of at least 30%.

The new link will comprise a dual carriageway with a bicycle lane, walkway and LED street lights.

A small waterfall on the hill will also be retained and construction would go around the waterfall.

Last month, MBPP mayor Datuk Yew Tung Seang said the construction on the paired road would take up RM44.2mil of the council’s budget next year. - The Star by Lo Tern Chern


Related:



Dosh: Stop-work order on elevated road project stays 

 

Public talks heading nowhere - Metro News



Penang Forum wants eco-review of PIL 1



The Tips and Procedures for Issuing a Stop Work Order


2 Things You Should Never Say To A Contractor - Residential ...




Related posts:



ART - Can be completed within 1 year for Penang lang, wait no more ! 年内就可以通车。槟城人,要不要?! The ART (Autonomous Rail-Rapid Transit) was nomi...


Penang bald Hillslopes a "time bomb"

 

Penang Paya Terubong Residents living under shadow of fear!

 

PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development 

 

IJM hill clearing & Trehaus construction damaged nearby houses since 2014 must be mitigated quickly

 

Friday, 22 May 2015

Blacklist the errant and greedy developer who destroyed old building in Penang

What a shame: A file photo of the entrance to the Prai market in Butterworth before it was demolished.

State govt wants firm which tore down market barred from building in Penang

GEORGE TOWN: The state government wants the developer who demolished the Prai market barred from undertaking future projects in Penang as well as disciplinary action against the police officer and lawyer for allegedly colluding with the builder.

Deputy Chief Minister ll Dr P. Ramasamy said the developer must be blacklisted and prevented from building in Penang for tearing down the 76-year-old market.

He said action must also be taken against the police officer whom he alleged had colluded with the developer during the demolition on May 17.

“I have written to the Penang police chief (Senior Deputy Comm Datuk Wira Abdul Rahim Hanafi) and the Home Ministry to investigate and take action against the police officer.

“I personally want the developer prosecuted and jailed and disciplinary action taken against the police officer who abetted the demolition which is a ‘daylight aggression’ and a total disregard for the law,” Dr Ramasamy said yesterday.

On the action sought against the developer’s lawyer, Dr Ramasamy claimed that the court order was for only the eviction of the people and not for demolition of the market.

“The Bar Council must act on this.”

He said there were plans to conserve the market as a heritage building but the demolition ‘threw a spanner into the works’ to restore the building.

Three police reports had been filed against the developer over the demolition.

The Seberang Perai Municipal Council has now cordoned off the site.

The case against the developer for violating the Town and Country Planning Act 1976 was mentioned in the Bukit Mertajam magistrate’s court yesterday and would be brought up again on June 23
- Nu R. Sekaran The Star/Asia News Network

No getting off the hook - Greedy developer should be taught a lession, Says DCM II

Deplorable: A filepic taken in June last year of the rundown Prai Market that was flattened on Sunday.

GEORGE TOWN: The state government will hold talks with the Seberang Prai Municipal Council on action to be taken against the developer for demolishing the 76-year-old Prai market.

Deputy Chief Minister II Dr P. Ramasamy said they would look into all avenues, including getting the developer to restore the structure and arch.

“We don’t have many buildings with heritage value on the mainland so we need to go all out to preserve these buildings.

“This greedy developer should be taught a lesson. The council has taken legal action against the developer before and I will ask them to do it again,” he said when contacted yesterday.

It was reported on Monday that a developer had demolished part of the 76-year-old Prai market despite a stop-work order being issued. The developer had gone against the council’s orders for a second time.

Dr Ramasamy was earlier quoted as saying that although the company managed to obtain vacant possession from the court in June last year, it still needed the council’s approval to carry out demolition work.

He said the state had identified the buildings surrounding the Prai market with heritage value, although it had not been gazetted yet.

A check by The Star showed that the arch at the market entrance with the year ‘1938’ on it was also torn down.

Meanwhile, a reader said it was disgraceful to read about the demolition by a developer who could not be bothered about heritage.

Sanjay C.S. said back in the early 70s, his mother used to cycle from their house in Jalan Baru to the market.

“And today, it resembles as if earthquake had struck there.

“In Nepal, their heritage was ruined by nature, but here, it was selfishly destroyed by human greed.

“The nonchalant developer should be heavily punished!” he said, adding that the state needed to protect its heritage buildings outside George Town as well. - By Tan Sin Chow The Star/Asia News Network

Destroyed despite MPSP's order - Prai market torn down, Penang govt wants action against developer

Destroyed: Workers demolishing the Prai market in Butterworth and (inset) the arch before it was torn down.

BUTTERWORTH: A developer has demolished part of the 76-year-old Prai market despite a stop-work order and the state government wants action taken against the firm.

What’s worse, the developer had gone against the Seberang Prai Municipal Council’s (MPSP) orders for a second time.

Deputy Chief Minister (II) Dr P. Ramasamy said the company managed to obtain vacant possession from the court in June last year but it still needed the council’s approval to carry out demolition work.

“I’ve instructed the council to take legal action against the company. The state government gazetted the buildings surrounding the Prai market, which have been identified as a building with heritage value.

“The workers moved in on Saturday morning and started to demolish the buildings during heavy rain when no one was around.

“This is the second time they’ve done this. They demolished three buildings the first time, and now four buildings,” he said yesterday.

Dr Ramasamy, who is also Prai assemblyman, said 50% of the compensation had been paid to the occupants and the rest would be paid when they move out.

“I would like to remind the company not to touch the Prai market as the council has listed it as a building with heritage value.”

Barber M. Thirunavakkarassu, 61, said he received a call from a friend at about 8am telling him that his shop was being demolished.

“I quickly rushed to my shop but it was too late. Someone could have gotten hurt as the electric supply was not disconnected,” he said.

A check by The Star showed that the arch at the market entrance with the year “1938’ on it was also torn down. MPSP president Datuk Maimunah Mohd Sharif said they would prepare the necessary documents so that the landowner-cum-developer could be charged in court for tearing down the buildings.

“This is the second time the developer had committed the offence without obtaining approval from us.

“The Town and Country Planning Act 1976 states that a planning approval is needed before a building is demolished,” she said at the council building in Bandar Perda, Bukit Mertajam.
- By M. SIVANANTHA SHARMA and CHRISTOPHER The Star/Asia News Network

Related post:

DEVELOPERS who carry out earthworks without approvals or permits from the Penang Island City Council (MBPP) could face the possibility of ...